Update - Metrolink Trafford Park Line – Temporary Traffic Regulation Orders – Parkway Circle

Guest User

Dear recipient

Update - Metrolink Trafford Park Line – Temporary Traffic Regulation Orders – Parkway Circle

Further to our previous email dated 7 July regarding essential work taking place on Parkway Circle.

The Metrolink contractor, Trafford Council and TfGM have reviewed the phasing of these works, and, as a result, have been able to reduce the lengths of time for some of the required road closures.

The work will now include some day working and lane restrictions.

 Please find below the plans detailing each phase of the works commencing from Monday 23 July.

33119-4.2-0047A Park Way Circle, Stretford (Surfacing Phasing) 

33119-4.2-0047B Park Way Circle, Stretford (Surfacing Phasing)

33119-4.2-0047C Park Way Circle, Stretford (Surfacing Phasing)

33119-4.2-0047D Park Way Circle, Stretford (Surfacing Phasing) 

33119-4.2-0047E Park Way Circle, Stretford (Surfacing Phasing) 

Please Note:

In all phases (1 to 4a/b) the colours represent the following:

Green – access routes open for all local traffic.

Red – lane and road closures

Blue – the work area of the contractor (MPT)

Please be aware that Phases 2 to 4a/b have both daytime and night time traffic management plans to detail the various road closures that will be in place.

These works represent the final stages in road surfacing, road line marking and testing and commissioning of the new/permanent traffic signals in this area.

We appreciate your patience during the construction of the Trafford Park Line.

If you have any family, friends, co-workers who you feel would benefit from being kept up to date with the project works, please forward the website details www.tfgm.com/MetrolinkTPL on to them.

TfGM will continue to engage with stakeholders along the route and will provide further information as we progress. In the meantime, if you have any queries regarding the scheme or if you would like to arrange a meeting, please contact either me or a member of the Metrolink team on 0161 244 1555 or email MetrolinkTPL@tfgm.com.  

Kind Regards

Angela Forster

Senior Communications Officer

Transport for Greater Manchester